In April 2020, as part of the overall Phase One budget of £44.6 billion set by the Department, HS2 Ltd planned to design and build the HS2 Euston station for £2.6 billion. This budget was lower than its £3 billion assessment of what the station would actually cost to build.16 We asked HS2 Ltd why it accepted a budget for the station that was so much lower than its estimate of what it would actually cost. HS2 Ltd told us that its estimate was based on a very high-level concept design and that ...
In April 2020, as part of the overall Phase One budget of £44.6 billion set by the Department, HS2 Ltd planned to design and build the HS2 Euston station for £2.6 billion. This budget was lower than its £3 billion assessment of what the station would actually cost to build.16 We asked HS2 Ltd why it accepted a budget for the station that was so much lower than its estimate of what it would actually cost. HS2 Ltd told us that its estimate was based on a very high-level concept design and that it agreed with the Department that it would have to come back and revisit the scope and costs at Euston. This was because there was lots of uncertainty a Type: conclusion | Number: 9 | Response status: not_addressed Government response: 2.1 The government agrees with the Committee’s recommendation. Target implementation date: Summer 2025 2.2 The objective of the Euston Reset Programme is to ensure that the scope of the HS2 station design is affordable and provides value for money to the taxpayer