Closed 82 of 367 events
Lifecycle stage Response Published
951 days in stage

HS2 Phase 2a Development

HS2 Phase 2a Development concerns the revised scope and delivery of the High Speed 2 rail project following the government's October 2023 decision to cancel Phase 2 and Phase 2b, leaving only Phase 1 (London to Birmingham) to proceed. Led by High Speed Two (HS2) Limited, the issue is active and involves developing a new business case, addressing West Coast Main Line capacity challenges, and coordinating the Euston station development with commercial and housing components.


Showing 82 of 367 signals
Family 1
Signal
Year
Body
Role
Clear all

2025

16 events
28 Feb 2025 | Committee report linked

HS2 Ltd told us that it is now seeking to renegotiate these contracts.32 It considers that the current contracts are unproductive and that reset provides the opportunity for a fair allocation of risk and an opportunity to find different ways of commercially incentivising the outcomes that it wants, rather than the ones that it is getting at the moment.33

HS2 Ltd told us that it is now seeking to renegotiate these contracts.32 It considers that the current contracts are unproductive and that reset provides the opportunity for a fair allocation of risk and an opportunity to find different ways …

2024

17 events
7 Feb 2024 | Committee report linked

We also asked whether any contracts would need to be cancelled in respect of Phase 2 and payments made to companies as a result. HS2 Ltd told us that for Phases 2a and 2b the number of contracts let was very small, but it was exposed to some legal challenge, the value of which exposure it estimated to be under £10 million.39

We also asked whether any contracts would need to be cancelled in respect of Phase 2 and payments made to companies as a result. HS2 Ltd told us that for Phases 2a and 2b the number of contracts let was …

7 Feb 2024 | Committee report linked

The Department confirmed it remains the Government’s ambition that Euston be the London terminus for HS2.48 But it confirmed it was still expecting trains to stop at Old Oak Common for a period of time before Euston was developed, because Euston would not be up and running in the same timeframe. The Department could not give any date or range of dates for when it thought Euston might be delivered.49

The Department confirmed it remains the Government’s ambition that Euston be the London terminus for HS2.48 But it confirmed it was still expecting trains to stop at Old Oak Common for a period of time before Euston was developed, because …

2023

18 events

2022

17 events
27 Jul 2022 | Committee report linked

We welcome the scale of the Government’s promised spending on improving rail in the North and the Midlands. £96 billion is a very substantial sum; it has the potential to transform rail travel for future generations and make a significant contribution to levelling up the country.

We welcome the scale of the Government’s promised spending on improving rail in the North and the Midlands. £96 billion is a very substantial sum; it has the potential to transform rail travel for future generations and make a significant …

27 Jul 2022 | Committee report linked

Whilst we recognise that the Golborne link was not perfect, and faced substantial local opposition, given its importance in terms of unlocking capacity for passengers and freight, and reducing journey times to Scotland, we are concerned that it has been cancelled without an alternative being proposed. The Department for Transport should set out alternative plans which add similar capacity as a minimum by March

Whilst we recognise that the Golborne link was not perfect, and faced substantial local opposition, given its importance in terms of unlocking capacity for passengers and freight, and reducing journey times to Scotland, we are concerned that it has been …

27 Jul 2022 | Committee report linked

To take account of the changes of plan for the HS2 Eastern leg and to inform current and future decision-making, the Department for Transport should publish by March 2023 an updated BCR for (a) the entire HS2 project and (b) the previous full proposals for the Eastern leg of HS2 Phase 2b. The methodology used must fully reflect impacts on regional inequalities.

To take account of the changes of plan for the HS2 Eastern leg and to inform current and future decision-making, the Department for Transport should publish by March 2023 an updated BCR for (a) the entire HS2 project and (b) …

27 Jul 2022 | Committee report linked

We welcome the Government’s pledge to look at how the Eastern leg of HS2 might be constructed in full to Leeds as originally planned; the city is a key focal point not only of existing rail networks, but of economic value and potential in the North.

We welcome the Government’s pledge to look at how the Eastern leg of HS2 might be constructed in full to Leeds as originally planned; the city is a key focal point not only of existing rail networks, but of economic …

27 Jul 2022 | Committee report linked

The Government must conduct its study on how best to take HS2 to Leeds urgently. We ask that a timetable for this work, including a firm date for the final report, be published by September 2022. This is essential for demonstrating that the commitment made to Leeds for high speed connections will be fulfilled. (Paragraph 47) Stations and cities

The Government must conduct its study on how best to take HS2 to Leeds urgently. We ask that a timetable for this work, including a firm date for the final report, be published by September 2022. This is essential for …

27 Jul 2022 | Committee report linked

The Government’s fixation on journey times as a benefit of the IRP must not overshadow the issue of capacity. It seems highly unlikely that an upgraded Victorian line can replicate the capacity increases achievable by building new track.

The Government’s fixation on journey times as a benefit of the IRP must not overshadow the issue of capacity. It seems highly unlikely that an upgraded Victorian line can replicate the capacity increases achievable by building new track. Type: conclusion …

27 Jul 2022 | Committee report linked

The Department for Transport should commission a full independent assessment of the seat and track capacity offered by the IRP, compared to the previous plans for HS2 and other options for NPR. This assessment must take into account the future effects on both long-distance and local passenger services, and freight capacity.

The Department for Transport should commission a full independent assessment of the seat and track capacity offered by the IRP, compared to the previous plans for HS2 and other options for NPR. This assessment must take into account the future …

2021

14 events